Construction started Monday for the Court & Laura streets improvement project being built by McCabe Construction of Eau Claire. Pulverizing the old asphalt was the first thing to be done followed by the closing of one lane of Monroe Street Wednesday morning so the tie-in could be accomplished for the new watermain. McCabe did a great job of making this as limited a disruption as possible by having the lane open for traffic again by midafternoon.

Mail: The contractor is following the directions given to them directly from the Post Office. The original plan from the Post Office and the Contractor was to put two groups of mailboxes out, one group at Monroe & Laura, and the other group at Kinnickinnic & Court. The mail carrier for that area said if someone has special needs to let them know and a solution would be arranged. Post Office 262-5166

**Mailboxes from 415 Kinni - 163 Court up to 288 Court are located at 458 Walnut
**Mailboxes from 477 - 480 - 554 - 557 Ash From 288 - 492 Court and 475 - 477 Sycamore are located at the east side corner of South St and Court St

Garbage: Set containers out next to construction area as close as you can to where you would normally place them. PIG will pick up as usual. Special needs will be helped by the Contractor and the Construction Inspector from Cedar corp.

The street and driveways will be open at all times for Court and Laura Street residents only. EXCEPT when the actual trenching activities for pipe installation occur in front of each lot or when the barricades completely close an area for such things as tree removals.There will also be a short time that driveways will not be accessible when the driveway aprons are poured and the concrete cures. Our goal is to have every driveway open every night.

Please bear with us. We are very fortunate that the weather is nice enough that the project could be started earlier than planned. The sooner we start, the sooner we finish.

WEEK ONE UPDATE 05/04:

Previously: McCabe has completed removals, 90% of water main installation (connection to Kinnickinnic Street remains) and 50% of water main testing.

This Week (05/04): McCabe will be working on sanitary sewer main this week starting at Walnut Street (continuing for 2-3 weeks).

Next Up: Next item will be sanitary and water laterals.

Traffic Restrictions: Court and Laura Streets are closed to through traffic. Cross streets are open to traffic but subject to periodic closures.

WEEK TWO UPDATE 05/11:

Last Week: Watermain testing continued and 40% of sanitary sewer installation has been completed.

This Week: McCabe will be continuing working on sanitary sewer main this week (continuing for 1-2 weeks).

Next Up: Next item will be sanitary and water laterals.

Traffic Restrictions: Court and Laura Streets are closed to through traffic. Cross streets are open to traffic but subject to periodic closures.

WEEK THREE UPDATE 05/18

Last Week: Watermain testing has been completed and 80% of sanitary sewer installation has been completed.

This Week: McCabe will be completing sanitary sewer main and starting sanitary and water laterals this week.

Next Up: Next item will be storm sewer.

Traffic Restrictions: Court and Laura Streets are closed to through traffic. Cross streets are open to traffic but subject to periodic closures.

WEEK FOUR UPDATE 05/25

This Week: Watermain and sanitary sewer installation has been completed (with the exception of the connection at Kinnickinnic which will be done last to reduce the distruption). Sanitary and water laterals have been started.

Next Week: Sanitary and water laterals will continue.

Next Up: Next item will be storm sewer.

Traffic Restrictions: Court and Laura Streets are closed to through traffic. Cross streets are open to traffic but subject to periodic closures.

WEEK FIVE UPDATE 06/01

Last Week: Sanitary and water laterals continued.

This Week: Sanitary and water laterals will be completed. Water and sewer connections at Kinnickinnic Street will occur mid-week. Storm sewer will start mid-week.

Next Up: Road building will commence after storm sewer is complete.

Traffic Restrictions: Court and Laura Streets are closed to through traffic. Cross streets are open to traffic but subject to periodic closures. The intersection of Kinnickinnic/Court will be closed or at least severely narrowed during water and sewer connections.

WEEK SIX UPDATE 06/08

Last Week: Completed sanitary and water laterals. Completed water and sewer connections at Kinnickinnic Street and Walnut Street. Started storm sewer.

This Week: Complete water and sewer connections at Ash Street. Continue storm sewer.

Next Up: Road building will commence after storm sewer is complete.

Traffic Restrictions: Court and Laura Streets are closed to through traffic. Cross streets are open to traffic but subject to periodic closures.

WEEK SEVEN UPDATE 06/15


Last Week: Completed water and sewer connection and storm sewer.

This Week: Will continue road building.

Next Up: Curb & gutter is tentatively scheduled to be installed next week. A letter was sent to residents last week warning them of the impending curb & gutter and the disruption it will cause to their access to their driveway (7 days).

Traffic Restrictions: Court and Laura Streets are closed to through traffic. Cross streets are open to traffic but subject to periodic closures.

WEEK EIGHT 06/22


This Week: Continued road building and installing concrete curb and gutter.

Next Week: Finishing concrete flatwork.

Next Up: After concrete is complete, contractor will start final grading activities.

Traffic Restrictions: Court and Laura Streets are closed to through traffic. Cross streets are open to traffic but subject to periodic closures.

WEEK 12 UPDATE 07/20

This Week: Restoring boulevards and installing asphalt driveways and surface course (currently scheduled for this Saturday).

Next Up: Saw & Seal and punchlist items.

Traffic Restrictions: Court and Laura Streets are closed to through traffic. Cross streets are open to traffic but subject to periodic closures.

Facebook Twitter Email

Other News in Home

Fire Truck 5

Welcome our New Fire Chief

Posted on: January 12, 2023
SnowyStreet2

Snow and Ice Reminder

Posted on: January 12, 2023
Drone City Sunset full

Current Projects

Posted on: July 1, 2022